The Naples Pier passed the halfway mark for its concrete on September 18, 2026, and crews have started on the first sections of decking. When it reopens, there won't be a concession stand. The pier going up at the west end of 12th Avenue South is stronger and higher than the one Hurricane Ian broke. Most of what used to keep people standing around at the entrance has been designed out, and that was intentional. City Council weighed noise, smells and crowds near the closest homes when it made the call. For Aqualane Shores, the pier is the closest Gulf landmark. The City puts the work at about 18 months. Until it's finished, the walk to the sand goes around it.
Where the Work Stands This October
The City of Naples keeps a dated log of the rebuild on its Naples Pier Rebuild Project page. Taken in order, the entries show how far the project has come since the groundbreaking on January 5, 2026:
- January 6: construction began.
- April 13: demolition of the old pier was finished.
- May 5: a month of diving work began to clear debris, including pilings buried since the 1990s.
- June 17: Shoreline Foundation began building a trestle on the south side so work could keep going when the offshore barges had to take shelter.
- June 26, July 9 and July 24: the first three concrete pours. About 200 cubic yards were in place after the third.
- September 18: the pour for the mid-pavilion took the project past 50 percent of the roughly 602 cubic yards of concrete the pier needs.
The next big change you'll see from the beach is the deck. Crews have built the first sections of decking, and two-thirds of the new ipe wood had arrived by late July. The City says the ipe goes on once all the concrete is poured. Benches and fish-cleaning stations come after the framing and decking. Work is also underway on electrical systems and on renovating the bathroom and storage building.
On August 14, Gulf Coast News reported the project at 40 percent complete, with city officials aiming for July 2027. That percentage and the City's concrete figure measure different things, so they don't conflict. City Manager Gary Young told the station the real schedule check comes after hurricane season: "Once we make it through hurricane season and we know the progress of the construction at that point, then you're in position to have a conversation if we are ahead or behind." Until then, July 2027 is a target, not a promised opening date.
Built to Outlast the Last One
What's going into the water explains why this rebuild is a replacement and not a repair. Ian reached land near Cayo Costa on September 28, 2022. The City says about 460 feet of the pier was badly damaged, and roughly 140 feet ended up on the Gulf floor, including the end shelter and more than 30 pilings. City engineers decided most of the structure was compromised and should be replaced in full.
| Feature | Pier before Ian | Pier under construction |
|---|---|---|
| Pile diameter | 14 inches | 18 inches |
| Deck elevation | Original height | Raised about 3 feet |
| Pile layout | Original spacing | Fewer piles, set farther apart |
| Decking support | Original | More concrete support under the ipe deck |
| Length | n/a | 805 feet into the Gulf |
| Food service | Concession over the water since 1946 | No concession stand |
The City says the wider spacing was chosen to reduce impacts on the shoreline. Turrell, Hall & Associates leads architecture and engineering with MHK Architecture, and Shoreline Foundation, Inc. is the builder. The pier dates to 1888 and has been rebuilt after storms in 1910, 1926, 1944 and 1960. It was renovated in 2015, then damaged by Irma in 2017 before Ian. The heavier piles and higher deck are the City's answer to that history.
The Food Stand Lost to the Neighbors
The last row of that table was the hardest fight of the rebuild, and it changes the pier more than any pile size. According to Naples Press, FEMA had already said a concession stand could not go back over the water, where one had stood since 1946. That left the land-side entrance as the only option. Council had already decided a concession, deck and seating at the entrance would make visitors cluster and block the flow onto the pier, and would bring noise and smells to nearby homes. A survey found a concession stand was not a top preference. Tim Hall of Turrell Hall & Associates also warned that changes over the water could restart federal review: "We lose our place in line."
At a June 16, 2025 workshop, Council told staff to shrink the land-side buildings and drop the concession and outdoor dining. The revised design came back to Council on March 4, 2026. According to the Gulf Coast News account of that meeting, some nearby residents had worried that a stand at the entrance would bring more crowds, traffic and food smells near their beachfront homes. Council members disagreed on the right answer:
"Mark my words, if we don't have concessions, we are going to get lambasted by our residents and our tourists." Council member Berne Barton
"And I would suggest that wheeling the cart for ice cream and water may be a fine solution. Having concessions is an absolute no for me." Council member Bill Kramer
Council approved the smaller land-side plan and asked staff to look into electrical service for a possible portable vendor. That means a cart for water and ice cream is being studied, not promised. The Naples Daily News summed it up as possible portable carts on land with limited offerings.
Here's what the approved entrance includes, based on the March 4 presentation:
- A small Beach Patrol office with its own restroom at the north men's restroom
- The old rear changing room turned into pier storage
- A small shaded area with benches and educational boards beside the south women's restroom
- Showers outside the shade structure, not under it
Gulf Coast News also reported less shaded seating on the south side and a small police substation with an accessible bathroom near the entrance. Each change shortens the time someone spends at the foot of the pier before walking out.
The Old Pier Went Offshore
The pier the neighborhood remembers didn't go to a landfill. On April 24, 2026, according to the City's April project update, 59 concrete pilings from the damaged pier, more than 300 tons in all, were placed at Wasmer Reef. The City describes the site as 10 miles offshore and part of a reef system started in 2015. The rest of the material went to a recycler to be turned into aggregate for future road projects.
Collier County's reef records differ a little. The County's reef location list logs the Naples Pier Reef at Wasmer as placed on April 27, 2026, at 250 tons. It lists the site at 40 feet deep, at 26° 2.029' N, 81° 58.585' W. A City and County planning presentation measured the distance as 10 nautical miles from Gordon Pass. The Collier County Artificial Reef Program is run by the Coastal Zone Management Department, which describes its reefs as habitat that adds to recreational and charter fishing and diving. In short, much of the pier that people used to fish from is now a place to fish over.
Getting to the Sand Until the Deck Opens
Until the pier reopens, these closures apply:
- Closed: the pier, its stairs, restrooms and showers, and 12th Avenue South west of Gulf Shore Boulevard South.
- Parking: only the western third of the pier lot at 12th Avenue South and Gulf Shore Boulevard South is open to the public. The eastern two-thirds is the construction yard.
- Beach access: pedestrian bypasses at the Broad Avenue South and 13th Avenue South beach ends stay open for the whole project, and both have restrooms.
From Aqualane Shores, the 13th Avenue South beach end is the closer of the two bypasses. From the sand there, the work is easy to follow, and the City's own September photos show brown pelicans resting on the new pilings between pours. The rest of the decking, the benches and the fish-cleaning stations are still to come, and the shaded benches at the entrance will be smaller than the ones that stood there before Ian.
I'm following the pier rebuild closely and can share what I'm seeing along this part of the shoreline. If you're wondering how the rebuild might affect an Aqualane Shores home, Mario Furillo is happy to talk it through. Let's Connect.